"The renewable energy industry is expanding in Australia with many career potentials."

www.goldwindglobal.com

www.goldwindglobal.com

"Goldwind is committed to helping Australia meet its renewable energy target."

"The communities support for renewable energy development will have a global impact on the reduction of carbon emissions."

"In 1 year of operating GRWF will offset 445 mega-tonnes of CO2."

Project Update

Construction Progress – November 2013

The construction program at GRWF is progressing with significant milestones being achieved; The final foundation was poured on 26th September which, along with the completion of almost all the onsite roads, means that the civil works involved on the project are now largely complete. This means that construction traffic will reduce significantly.

The switchyard for the project which connects the project to the TransGrid transmission network is now
complete with the contractors (UGL) now demobilising from the site. This is a significant achievement which allows the project to export green energy to customers on the network.

The delivery of the components will be extended to a further 10 weeks. As with the current delivery schedules,
all loads will be carried through in the early hours and under Police escort to ensure minimal disruption to the local communities of Goulburn and Upper Lachlan Shire.

Goldwind would like to thank the communities surrounding Gullen Range Wind Farm for their ongoing patience and support during the project.

Construction start 17 September 2012

Construction of the Gullen Range Wind Farm (the Project) is scheduled to commence on Monday 17 September 2012, with an anticipated 14 month construction period. Catcon and Consolidated Power Projects have been engaged by Gullen Range Wind Farm to undertake construction of the Project.

What to expect

The construction of the Project will involve the following key activities:

Early works approximately 17 September 2012 to 1 October 2012

  • implementation of environmental management controls
  • establishment of temporary site offices and facilities
  • upgrading of onsite roads
  • transportation of people and equipment to site
  • construction of temporary site offices and facilities.

 

Construction approximately 1 October 2012 to December 2013

  • transportation of people, materials and equipment to site
  • civil works for access track construction, footings and trenching for cables
  • preparation of hardstand areas
  • laying cables
  • preparation of the concrete footings
  • establishment, operation and removal of concrete batching plants
  • installation of wind turbines using large mobile cranes
  • construction of a substation and onsite power reticulation lines and cables
  • temporary site storage.

 

Commissioning approximately December 2013 – March 2014

  • pre-commissioning checks on all high-voltage equipment
  • connection to the grid.

Demobilisation approximately commencement December 2013

  • demobilisation and rehabilitation of site compounds
  • removal and rehabilitation of temporary road alignments.

Plant and machinery that will be operated during these periods includes trucks, graders, excavators, backhoes, bulldozers, rollers, cranes, water carts, power tools, lighting towers and generators.

Work on site will generally take place during standard construction hours as follows:

  • Monday to Friday: 7am – 6pm
  • Saturday: 8am – 1pm

Should works be required out of these hours, for example night erection of turbines as a result of strong winds during the day, members of the community will be notified in advance